2015 | Awarded Noida Metro Project : NC-03 Part Design and Construction of Elevated Viaduct and 6 elevated stations viz. Knowledge Park II, Pari Chowk, Alpha 1, Alpha 2, Delta 1, Depot Station, and connection to Depot including architectural finishing works of stations from chainage 19322.9 m to 29569 m of Noida-Greater Noida Metro Project. |
2015 | Awarded Noida Metro Project : NC-02 Part Design and Construction of Elevated Viaduct and 7 elevated stations viz. Sector 142, Sector 143, Sector 144, Sector 147, Sector 153, Sector 146 and Sector 149 including architectural finishing works of stations from chainage 9129.8 m to 19322.9 m of Noida-Greater Noida Metro Project. |
2015 | Awarded Noida Metro Project : NC-01 Part Design and Construction of elevated viaduct and 8 elevated stations viz. Sector 71, Sector 50, Sector 78, Sector 101, Sector 81, Dadari Road, Sector 83, sector 137, including Architectural Finishing works of stations from Chainage (-) 450 m to 9129.8 m of Noida-Greater Noida Metro Project. |
2013 | Awarded Jaipur Metro (Phase 1B) Project : Construction of Tunnel by TBM between Chandpole and Badi Chouper, having twin tunnels of 2.8 Kms and 5.8 meters finished diameter, underground stations at Choti Chouper and Badi Chouper by Cut & Cover Method on East-West Corridor. |
2013 | Awarded PWD Project : The Outer Ring Road Work from Km 7+644 to Km 0+000 in Delhi between Mukarba Chowk to Wazirabad Chowk. The scope of project includes construction of flyovers, loops, bridges, widening of road on embankment, etc. |
2011 |
Awarded Delhi Metro Project : CC - 04 Underground Section between Mukundpur and Shalimar Bagh having twin tunnels of 2.145 kms and 5.80 meters finished diameter, underground station at Azadpur, Cut & Cover Tunnel and Ramp at both Ends. |
2010 |
Awarded Bangalore Metro project between City Railway Station and Cricket Stadium, having twin tunnels of 4.45 kms and 5.6 meters internal finsihed diameter with four under ground stations, INDIA |
2007 |
Awarded Delhi Metro project between Green Park and Udyog Bhawan, having twin tunnels of 8 kms and 5.8 meters internal diameter with four under ground stations, INDIA |
2007 |
Four laning of Hyderabad-Bangalore Section from km293.4 to km 336 of NH-44 in the State of Andhra Pradesh - ADB-II/C-12, INDIA |
2007 |
Four laning of Hyderabad-Bangalore Section from km336 to km 376 of NH-44 in the State of Andhra Pradesh - ADB-II/C-13, INDIA |
2006 |
Outer Ring Road in Hyderabad; Construction of six/eight lane access controlled Expressway as Outer Ring Road to Hyderabad City. Package No-II (From Km 11.000 to 24.380), INDIA |
2006 |
Konkan Railway Project - Construction of Civil Works (km30/000 - km50/400) of Single BG Line on Katra-Loale Section Under USBRL Project. |
2006 |
SEZ in Andhra Pradesh - Construction of all the buildings covering Factory Buildings, Office Buildings and Utility Buildings for Apache Footwear company, production house for Adidas Shoe, in various phases. |
2005 |
East West NH Corridor Project- Package EWII (RJ-7), Rehabilitation and Upgrading of Km 253.000 to Km 316.000 of NH-76 to 4-Lane Configuration in the State of Rajasthan. |